Well D Construction

The Town has completed the design of the proposed Well D project which will connect a new well to the Town's main water system located in the northwest corner of the Town. Once developed, Well D will be the Town's largest producing well in our system at 165 GPM and will replace a developer built well known as Well 21 NB. The Town has acquired the easement from RHOA to complete this capital project. Last month the Town awarded the construction contract to Lantz Construction Company of Winchester with work scheduled to begin in September of 2023. The new well should be available for reserves and use in December of 2023.